Projects

Chipata Central Constituency

Road Grading in all wards area

Status: ongoing

Source of financing: Constituency Development Fund

Start Date: 1st October 2025

End Date: 20th December 2025

Total Project Cost: k3,200,000

Luangeni Constituency

Makwe School Construction

Status: ongoing

Source of financing: Constituency Development Fund

Start Date: 28 September 2024

End Date: 31st December 2025

Total Project Cost: K1,033,317.60

Chipata Central Constituency

Newly Constructed Comesa Market

Status: ongoing 

Source of financing: European Union

Start Date: 2nd January 2024

End Date: 31 December 2025

Total Project Cost: US $985,920.33

Luangeni Constituency

Kazimomwe Health Post Chikando Ward

Status: Completed

Source of financing: Constituency Development Fund

Start Date: 2nd January 2024

End Date: 22nd April 2024

Total Project Cost: k780,199.2

Luangeni Constituency

Chief Nzamane Palace

Status: Completed

Source of financing: Constituency Development Fund

Start Date: 8th January 2024

End Date: 9th July 2025

Total Project Cost: K4,038,239.49

Chipata Central Constituency

Market Shelters and Bus Station Construction

Status: Ongoing

Source of financing: KFW Bank

Start Date: 2nd December 2024

End Date: 2nd Dember 2025

Total Project Cost: K42,627,398.50

IMG-20251113-WA0039

Luangeni Constituency

Mtizwa school 1×3 classroom block

Status: Completed

Source of financing: Constituency Development Fund

Start Date: 20th January 2025

End Date: 20th May 2025

Total Project Cost: k 943,662.83 

Luangeni Constituency

Construction of Kamwa 1×3 Classroom block Makangila Ward

Status: Ongoing

Source of financing: Constituency Development Fund

Start Date: 2nd June 2025 January 2025

End Date: 9th January 2026

Total Project Cost: K 950,000

Luangeni Constituency

Construction of Low Cost Staff House Mtowe school  Makangila Ward

Status: Completed

Source of financing: Constituency Development Fund

Start Date: 10th October  2024

End Date: 10th February 2025

Total Project Cost: K 950,000

Chipata Central Constituency

Construction of 1×3 Chigumu Primary School Msanga Ward

Status: Ongoing

Source of financing: Constituency Development Fund

Start Date: 12th September 2025

End Date: 5th January 2025

Total Project Cost: K 950,000